RAILCOP

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A)         Construction of 160 km at high speed track from Hofuf to Khurais

            in Saudi Arabia.

 

Year of Completion :                 1986

Cost                                        US$ 100.0 million

 

The project involved construction of 160 km length of railway line comprising UIC 60-Kg rails, vossloh fastenings and pre-stressed mono block concrete sleepers.

 

The track laying work was fully mechanised. The rail joints were welded by on-site flash butt welding and thermit welding processes.

 

The project involved 12 million cubic meters of earthwork comprising of 7 million cubic meters of earth-fill and 5 million cubic meters of excavation including rock cutting/blasting.

 

Maximum height of the embankment was 28 meters whereas the cutting went to a maximum depth of 23.5 meters. Rock blasting was carried in an area criss-crossed by oil/gas pipe lines which required controlled blasting. Quantity of excavation requiring blasting exceeded 2.5 million cubic meters.

 

The project included :

 -          One major pre-stressed concrete road under bridge

-            -          Two major pre-stressed concrete road-over bridges

-            -          43 RCC box culverts

-            -          Sixteen oil/gas pipe crossings

-            -          Five overhead power line crossings

-            -          Three crossing stations

 

In addition, colony for staff was also constructed as a part of the project.

 


 

B)        Construction of 20 km Railway Siding at Al-Kharj, Saudi Arabia.

 

Year of Completion :               1983

Cost                                      Saudi Riyals 31.0 million

 

The project involved construction of railway siding having a length of 20 km. The work comprised construction of railway line with UIC 54 kg rails, vossloh fastenings and concrete sleepers. Rails were continuously welded.

The project included earthwork of about 200,000 cubic meters, construction of ARMCO pipe culverts, level crossings and other ancillary works.

 


C)        Construction of Rail Spur from Taftan to Saindak, Pakistan (35 KM)

 

Year of Completion :               1995

Cost                                      Rs. 231.0 million

           

The project involved construction of 35 km length of railway line for copper-gold Saindak project. The siding has steep grades (upto 2%) and sharp curves. Track consists of 37.5 kg rails laid on twin block concrete sleepers.

 


D)        End Cropping/Welding of Rails in Saudi Arabia.

 

Year of Completion :               1995

Cost                                      Saudi Riyal 12.0 million

 

The project comprised end cropping of 105 km of rails on Line No.2 between Hofuf and Al-Kharj. Rails were welded by thermit process to form continuous welded rails.

 


 

E)        Construction of Fatima Jinnah Road Over Bridge, Karachi, Pakistan

 

Year of Completion                 1998

Cost                                      Rs. 190.0 million

 

The project involved construction of 1800 feet long six lanes dual carriage-way bridge on main railway line. The work comprised construction of 184 presteressed concrete girders and 266 piles.

 


F)         Construction of Rashid Minhas Road Fly-over Bridge, Pakistan

 

Year of Completion :               2000

Cost                                      Rs. 300.0 million

 

The work comprised construction of 1517 meter long two way flyover bridges with 609 pre-stressed concrete girders and 335 piles of 750 mm diameter.

 


 

G)        End-Cropping/Welding of Rails in Saudi Arabia

 

Year of Completion :               2002

Cost                                      Saudi Riyals 9.0 million

 

            The project comprised welding of rails by Thermit process to form continuous welded rails on Line No.2 between Hofuf and Al-Kharj.  

 


H)          Construction of Two Sub-Way Bridges at Peshawar

 

Year of Completion                 2003

Cost                                      Rs.32.0 million

 

            The project comprises construction of two sub-ways at Peshawar Cantt.   

 


I)         Construction of Margala Dry Port at Islamabad

 

Year of Completion                 2004

Cost                                      Rs.20.0 million