                Client  : SAUDI RAILWAYS ORGANIZATION (SRO)

 

 

 

 

Sr Description

Year of Completion

Contract Value (SR in million)

1

Construction of 20 Km Railway Track for Ministry of Defense at Al-Kharj 1983 31.0

2

Construction of 160 KM High Speed Track from Hofuf to Khurais 1986 375.0

3

Construction of 18 box culverts on existing Dammam-Riyadh Line 1986 1.0

4

Construction of 2 KM Base Siding at Al-Kharj   1987 1.0

5

Construction of 2.4 KM Railway Siding at Abqaiq 1988 1.0

6

Construction of Barley Siding Project near Al-Kharj 1990 2.0

7

Construction of Barley Siding 1992 0.3

8

End-Cropping/Welding of Rails 1995 12.0

9

End-Cropping/Welding of rails of 71 km of Main Line Track on Dammam–Al-Kharj–Riyadh Section   2002 9.0