RAILCOP |
|
|
|
|
||
|
Position at Takeover Stage ► RAILCOP took over the Track Machine Shops on July 1, 2001. ► Pakistan Railways had six Duomatic Machines, which were all overdue for complete overhauling. ► Pakistan Railways had three PU Machines of 1982 make, requiring heavy reconditioning.
Steps Taken by RAILCOP ► RAILCOP inducted Electronics and Mechanical Engineers. ► Inducted Diploma Holders for quality improvement. ► Imported genuine spare parts from international manufacturers. ► Established Laboratory, provided qualified quality control staff, audio/video training facilities. ► Rehabilitated workshop building, store & civil physical infrastructure. ► Brought in order a number of machines lying out of order since long.
|
||
| Track Machine before Repair | Track Machine after Repair | |
|
|
|
|
|
|
|
|
|
|
|
|